Sierra SunTower CSP Project
This page provides information on Sierra SunTower CSP project, a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration.
Project Overview
Power Station: | Sierra SunTower |
---|---|
Location: | Lancaster |
California United States | |
Owners (%): | eSolar |
Technology | Power Tower |
Nominal Capacity: | 5 MW |
Status | Currently Non-Operational |
Status Date
Status Date |
---|
Background
Lat/Long Location | 34.731,-118.139 |
---|
Participants
Developer |
eSolar USA |
---|---|
Operator | eSolar |
Electricity Generation Offtaker | Southern California Edison |
Construction Job Years | 130 |
Annual Operations Jobs | 12 |
Costs
Concessional Funding or Other Support | Expected 30% Federal Investment Tax Credit (ITC, 5-year MACRS) |
---|
Plant Configuration
Solar Field
Solar Field Aperture Area (m²) | 27670 |
---|---|
# of Heliostats (or dishes for dish systems) | 24360 |
Heliostat Aperture Area (m²) (or dish aperature for dish systems) | 1 |
Collector/Heliostat Engineering or IP Owner |
eSolar USA |
Solar Field (Receiver)
Receiver Working Fluid | Water |
---|---|
Receiver Working Fluid Category | Water |
Tower Height (m) | 55 |
Receiver Manufacturer |
Babcock & Wilcox |
Receiver Model | External - Dual-cavity receiver & tubular external receiver |
Power Block
Nominal Turbine or Power Cycle Capacity | 5 MW |
---|---|
Power Cycle | Steam Rankine |
Cooling Type | Wet |