SIDC Ruoqiang 100MW Tower + 900MW PV CSP Project
This page provides information on SIDC Ruoqiang 100MW Tower + 900MW PV CSP project, a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration.
Project Overview
Power Station: | SIDC Ruoqiang 100MW Tower + 900MW PV |
---|---|
Location: | Ruoqiang |
Bayingolin | |
Xinjiang (XUAR) China | |
Technology | PV-Hybrid, Tower |
Solar Resource: | 1767 |
Nominal Capacity: | 100 MW |
Status | Under Construction |
Start Year: | 2025 |
Status Date
Status Date |
---|
Background
Break Ground Date | 2023 |
---|---|
Expected Generation (GWh/year) | 150.6 |
Participants
Developer |
State Development and Investment Corporation (SDIC) China |
---|---|
EPC |
North China Electric Power Design Institute (NCEPDI) of CEEC, Shouhang Hi-Tech China |
Construction Job Years | 2000 |
Costs
Total Construction Cost (2022) | 1690.00 million | ||
---|---|---|---|
Total Cost USD (2020) | $251.3 million | ||
Specific Cost/kW USD (2020) | $ 2513 | ||
LCOE USD/kWh (2020) | $ 12 | ||
Levelised cost of electricity with 5% weighted average cost of capital and a 25 year payback period, capacity dependent O&M (1.5% of investment cost per year), deflated from Year_operational using the Worldbank's GDP deflator; if station under development or construction then not deflated (assumed cost year 2020) | |||
Policy Support Scheme | Subsidy free, supported by provincial coal tariff. |
Plant Configuration
Solar Field
Collector/Heliostat Engineering or IP Owner |
Shouhang China |
---|
Solar Field (Receiver)
Receiver Working Fluid | Molten Salt |
---|---|
Receiver Working Fluid Category | Salt |
Power Block
Nominal Turbine or Power Cycle Capacity | 100 MW |
---|---|
Turbine Manufacturer |
Dongfang China |
Thermal Energy Storage
Storage Capacity (Hours) | 8 |
---|---|
Storage Description | Molten Salt |