CNNC Yumen 100MW Fresnel + 400MW PV + 200MW Wind CSP Project
This page provides information on CNNC Yumen 100MW Fresnel + 400MW PV + 200MW Wind CSP project, a concentrating solar power (CSP) project, with data organized by background, participants, and power plant configuration.
Project Overview
Power Station: | CNNC Yumen 100MW Fresnel + 400MW PV + 200MW Wind |
---|---|
Location: | Yumen |
Jiuquan | |
Gansu China | |
Owners (%): | Yumen Xin’ao New Energy Co., Ltd., a joint venture of Gansu Bocheng Tongda Energy Co., Ltd and and Shaanxi Xinhua Water Conservancy and Hydropower Investment Co., Ltd., the latter a subsidiary of CNNC Xinhua Hydropower Co. Ltd |
Technology | Wind-PV-Hybrid, Fresnel |
Solar Resource: | 1641 |
Nominal Capacity: | 100 MW |
Status | Under Construction |
Start Year: | 2023 |
Status Date
Status Date |
---|
Background
Break Ground Date | 2022 |
---|
Participants
Developer |
Northwest Electric Power Design Institute (NWEPDI), Dunhuang Dacheng Shengneng New Energy Technology China |
---|---|
EPC |
NWEPDI of CEEC China |
Electricity Generation Offtaker | Gansu State Grid Electric Power |
Costs
Remuneration RMB/kWh | 0.31 | ||
---|---|---|---|
Remuneration Start Year | 2021 | ||
Remuneration USD/kWh Deflated (2020) | 0.05 | ||
Support Scheme Type | FIT | ||
Policy Support Scheme | Subsidy free, supported by provincial coal tariff. |
Plant Configuration
Solar Field
Solar Field Aperture Area (m²) | 1300000 |
---|---|
Collector/Heliostat Engineering or IP Owner |
Lanzhou Dacheng China |
Solar Field (Receiver)
Receiver Working Fluid | Molten Salt |
---|---|
Receiver Working Fluid Category | Salt |
Power Block
Nominal Turbine or Power Cycle Capacity | 100 MW |
---|
Thermal Energy Storage
Storage Capacity (Hours) | 8 |
---|---|
Storage Description | Molten Salt |
TES Engineering Company | Bluestar (Beijing) Chemical Machinery Co., Ltd. |