NOOR III

Status Date

Background

Technology
Power Tower
Status
Operational
Location

Ouarzazate
Morocco

Lat/Long Location
31°
3'
37.00"
North
52'
13.00"
West
Break Ground Date
Start Production Date
PPA/Tariff Rate
1.42 MAD per kWh
PPA/Tariff Information
USD 0.15 kWh

Participants

Developer(s)
ACWA
EPC Contractor
Sener - SEPCOIII
Generation Offtaker(s)
ONE

Plant Configuration

Solar Field

Heat-Transfer Fluid Type
Molten salt

Power Block

Turbine Capacity (Gross)
150 MW
Turbine Capacity (Net)
134 MW
Output Type
Steam Rankine

Thermal Storage

Storage Type
2-tank direct
Storage Capacity
7 hours
Storage Description
Molten salt

Project Overview

Project Name: NOOR III
Location: Morocco
Technology: Power Tower
Turbine Capacity (Net):
134 MW
Turbine Capacity (Gross):
150 MW
Status: Operational
Start Year: 2018